Saturday, August 31, 2013

View from Balcony, Ghaghar, Pkl IT Park, and Mountain side

Panchkula IT Park, Sector 22, One of the several underconstruction IT Park Building(AnantRaj IT Park) [view from  4th floor]
Ghaghar View
Mountain View [opposite Ghaghar view]
Front facing [Panchkula Golfcourse, Devilal Stadium & Ghaghar view]



Latest Photos






Sunday, April 14, 2013

April 2013 outerview / elevation of The New Ashirwad CGHS Ltd. Sector 23 Panchkula

Happy Baisakhi to All of you !! The flooring of the society is being done and 50% of work of flooring is complete. the sanitary, electricity work, new transformer, generator , common lighting etc. is left. God knows when the apartments would be handed over. the delay is too much now..
Elevation of Building as on 13 April 2013




Construction Progress as in November 2012

The following photos show the progress on 28.11.2012;

FireFighting Equipment in Basement

Basment entrance

Scaffolding for pipe cover

Cable trays in Basement

Inside of an Apartment

Lift entry to be tiled

Room of an Apartment

Tuesday, July 3, 2012

New Ashirwad Group Housing Society in Sector 23 Panchkula. opp. Gurudwara Nada Sahib

The Society flats at The New Ashirwad CGHS Ltd, Sector 23 Panchkula, Haryana are under construction since December 2009.




The 7 floor building is situated on Polt No. 2A, Opposite the upcoming Panchkula IT Part in sector 22 and Ghaghar river. The Building is near to Bhai MatiDass Society and Gurudwara Nadda Sahib Ji.

The Society will have 28  three bed room apartments with basement also. The approx. area of each flat is around 1450-1500 sq.ft.

Progress:
Floor tiles: As on date, the floor tiles, kota stone in balconies, marble in common area between flats(first floor onwards) is over.
Stair Cases :  marble on stair case is being laid.
Doors and windows : The wooden doors are being erected.the iron jali doors are fitted.
Plumbing and sanitation work : Main pipes are laid. but terminations and per flat fittings is to be done yet.
Lift: Material for one lift has arrived long back (7-8 months). this is yet to be fitted.
Cement plaster on building: Plastering has been done through out now. only small patches needs to be filled.
Iron grills in the balconies: The iron railings are fitted.

The progress is very slow since last August. The society has already missed the possession deadline on June 2011.

I hope that the possession of flat will happen only in 2013 some time.

Sunday, November 6, 2011

Progess of Work as in August 2011






Here are some pics of progress of work as on 28 August 2011